American
Recovery and Reinvestment Act of 2009 -
Energy and Water
| Title IV - Energy and Water Development -------------------------------------------------------------------------------- DEPARTMENT OF DEFENSE—CIVIL DEPARTMENT OF THE ARMY CORPS OF ENGINEERS—CIVIL INVESTIGATIONS |
|
CONSTRUCTION
For an additional amount for ‘‘Construction’’, $2,000,000,000: Provided, That not less than $200,000,000 of the funds provided
H. R. 1—21
shall be for water-related environmental infrastructure assistance: Provided further, That section 102 of Public Law 109–103 (33 U.S.C. 2221) shall not apply to funds provided in this title: Provided further, That notwithstanding any other provision of law, funds provided in this paragraph shall not be cost shared with the Inland Waterways Trust Fund as authorized in Public Law 99–662: Provided further, That funds provided under this heading in this title shall only be used for programs, projects or activities that heretofore or hereafter receive funds provided in Acts making appropriations available for Energy and Water Development: Provided further, That funds provided under this heading in this title shall be used for programs, projects or activities or elements of programs, projects or activities that can be completed within the funds made available in that account and that will not require new budget authority to complete: Provided further, That the limitation concerning total project costs in section 902 of the Water Resources Development Act of 1986, as amended (33 U.S.C. 2280), shall not apply during fiscal year 2009 to any project that received funds provided in this title: Provided further, That funds appropriated under this heading may be used by the Secretary of the Army, acting through the Chief of Engineers, to undertake work authorized to be carried out in accordance with section 14 of the Flood Control Act of 1946 (33 U.S.C. 701r); section 205 of the Flood Control Act of 1948 (33 U.S.C. 701s); section 206 of the Water Resources Development Act of 1996 (33 U.S.C. 2330); or section 1135 of the Water Resources Development Act of 1986 (33 U.S.C. 2309a), notwithstanding the program cost limitations set forth in those sections: Provided further, That for projects that are being completed with funds appropriated in this Act that would otherwise be expired for obligation, expired funds appropriated in this Act may be used to pay the cost of associated supervision, inspection, overhead, engineering and design on those projects and on subsequent claims, if any: Provided further, That the Secretary of the Army shall submit a quarterly report to the Committees on Appropriations of the House of Representatives and the Senate detailing the allocation, obligation and expenditures of these funds, beginning not later than 45 days after enactment of this Act: Provided further, That the Secretary shall have unlimited reprogramming authority for these funds provided under this heading.
MISSISSIPPI RIVER AND TRIBUTARIES
For an additional amount for ‘‘Mississippi River and Tributaries’’, $375,000,000: Provided, That funds provided under this heading in this title shall only be used for programs, projects or activities that heretofore or hereafter receive funds provided in Acts making appropriations available for Energy and Water Development: Provided further, That funds provided under this heading in this title shall be used for programs, projects or activities or elements of programs, projects or activities that can be completed within the funds made available in that account and that will not require new budget authority to complete: Provided further, That the limitation concerning total project costs in section 902 of the Water Resources Development Act of 1986, as amended (33 U.S.C. 2280), shall not apply during fiscal year 2009 to any project that received funds provided in this title: Provided further, That for projects that are being completed with funds appropriated
H. R. 1—22
in this Act that would otherwise be expired for obligation, expired funds appropriated in this Act may be used to pay the cost of associated supervision, inspection, overhead, engineering and design on those projects and on subsequent claims, if any: Provided further, That the Secretary of the Army shall submit a quarterly report to the Committees on Appropriations of the House of Representatives and the Senate detailing the allocation, obligation and expenditures of these funds, beginning not later than 45 days after enactment of this Act: Provided further, That the Secretary shall have unlimited reprogramming authority for these funds provided under this heading.
OPERATION AND MAINTENANCE
For an additional amount for ‘‘Operation and Maintenance’’, $2,075,000,000: Provided, That funds provided under this heading in this title shall only be used for programs, projects or activities that heretofore or hereafter receive funds provided in Acts making appropriations available for Energy and Water Development: Provided further, That funds provided under this heading in this title shall be used for programs, projects or activities or elements of programs, projects or activities that can be completed within the funds made available in that account and that will not require new budget authority to complete: Provided further, That section 9006 of Public Law 110–114 shall not apply to funds provided in this title: Provided further, That for projects that are being completed with funds appropriated in this Act that would otherwise be expired for obligation, expired funds appropriated in this Act may be used to pay the cost of associated supervision, inspection, overhead, engineering and design on those projects and on subsequent claims, if any: Provided further, That the Secretary of the Army shall submit a quarterly report to the Committees on Appropriations of the House of Representatives and the Senate detailing the allocation, obligation and expenditures of these funds, beginning not later than 45 days after enactment of this Act: Provided further, That the Secretary shall have unlimited reprogramming authority for these funds provided under this heading.
REGULATORY PROGRAM
For an additional amount for ‘‘Regulatory Program’’, $25,000,000.
FORMERLY UTILIZED SITES REMEDIAL ACTION PROGRAM
For an additional amount for Formerly Utilized Sites Remedial Action Program, $100,000,000: Provided, That funds provided under this heading in this title shall be used for programs, projects or activities or elements of programs, projects or activities that can be completed within the funds made available in that account and that will not require new budget authority to complete: Provided further, That for projects that are being completed with funds appropriated in this Act that would otherwise be expired for obligation, expired funds appropriated in this Act may be used to pay the cost of associated supervision, inspection, overhead, engineering and design on those projects and on subsequent claims, if any: Provided further, That the Secretary of the Army shall submit a quarterly report to the Committees on Appropriations
H. R. 1—23
of the House of Representatives and the Senate detailing the allocation, obligation and expenditures of these funds, beginning not later than 45 days after enactment of this Act: Provided further, That the Secretary shall have unlimited reprogramming authority for these funds provided under this heading.
DEPARTMENT OF THE INTERIOR
BUREAU OF RECLAMATION
WATER AND RELATED RESOURCES
For an additional amount for ‘‘Water and Related Resources’’, $1,000,000,000: Provided, That of the amount appropriated under this heading, not less than $126,000,000 shall be used for water reclamation and reuse projects authorized under title XVI of Public Law 102–575: Provided further, That funds provided in this Act shall be used for elements of projects, programs or activities that can be completed within these funding amounts and not create budgetary obligations in future fiscal years: Provided further, That $50,000,000 of the funds provided under this heading may be transferred to the Department of the Interior for programs, projects and activities authorized by the Central Utah Project Completion Act (titles II–V of Public Law 102–575): Provided further, That $50,000,000 of the funds provided under this heading may be used for programs, projects, and activities authorized by the California Bay-Delta Restoration Act (Public Law 108–361): Provided further, That not less than $60,000,000 of the funds provided under this heading shall be used for rural water projects and shall be expended primarily on water intake and treatment facilities of such projects: Provided further, That not less than $10,000,000 of the funds provided under this heading shall be used for a bureau-wide inspection of canals program in urbanized areas: Provided further, That the costs of extraordinary maintenance and replacement activities carried out with funds provided in this Act shall be repaid pursuant to existing authority, except the length of repayment period shall be as determined by the Commissioner, but in no case shall the repayment period exceed 50 years and the repayment shall include interest, at a rate determined by the Secretary of the Treasury as of the beginning of the fiscal year in which the work is commenced, on the basis of average market yields on outstanding marketable obligations of the United States with the remaining periods of maturity comparable to the applicable reimbursement period of the project adjusted to the nearest one-eighth of 1 percent on the unamortized balance of any portion of the loan: Provided further, That for projects that are being completed with funds appropriated in this Act that would otherwise be expired for obligation, expired funds appropriated in this Act may be used to pay the cost of associated supervision, inspection, overhead, engineering and design on those projects and on subsequent claims, if any: Provided further, That the Secretary of the Interior shall submit a quarterly report to the Committees on Appropriations of the House of Representatives and the Senate detailing the allocation, obligation and expenditures of these funds, beginning not later than 45 days after enactment of this Act: Provided further, That the Secretary shall have unlimited reprogramming authority for these funds provided under this heading.
H. R. 1—24
DEPARTMENT OF ENERGY
ENERGY PROGRAMS
ENERGY EFFICIENCY AND RENEWABLE ENERGY
For an additional amount for ‘‘Energy Efficiency and Renewable Energy’’, $16,800,000,000: Provided, That $3,200,000,000 shall be available for Energy Efficiency and Conservation Block Grants for implementation of programs authorized under subtitle E of title V of the Energy Independence and Security Act of 2007 (42 U.S.C. 17151 et seq.), of which $2,800,000,000 is available through the formula in subtitle E: Provided further, That the Secretary may use the most recent and accurate population data available to satisfy the requirements of section 543(b) of the Energy Independence and Security Act of 2007: Provided further, That the remaining $400,000,000 shall be awarded on a competitive basis: Provided further, That $5,000,000,000 shall be for the Weatherization Assistance Program under part A of title IV of the Energy Conservation and Production Act (42 U.S.C. 6861 et seq.): Provided further, That $3,100,000,000 shall be for the State Energy Program authorized under part D of title III of the Energy Policy and Conservation Act (42 U.S.C. 6321): Provided further, That $2,000,000,000 shall be available for grants for the manufacturing of advanced batteries and components and the Secretary shall provide facility funding awards under this section to manufacturers of advanced battery systems and vehicle batteries that are produced in the United States, including advanced lithium ion batteries, hybrid electrical systems, component manufacturers, and software designers: Provided further, That notwithstanding section 3304 of title 5, United States Code, and without regard to the provisions of sections 3309 through 3318 of such title 5, the Secretary of Energy, upon a determination that there is a severe shortage of candidates or a critical hiring need for particular positions, may from within the funds provided, recruit and directly appoint highly qualified individuals into the competitive service: Provided further, That such authority shall not apply to positions in the Excepted Service or the Senior Executive Service: Provided further, That any action authorized herein shall be consistent with the merit principles of section 2301 of such title 5, and the Department shall comply with the public notice requirements of section 3327 of such title
5.
ELECTRICITY DELIVERY AND ENERGY RELIABILITY
For an additional amount for ‘‘Electricity Delivery and Energy Reliability,’’ $4,500,000,000: Provided, That funds shall be available for expenses necessary for electricity delivery and energy reliability activities to modernize the electric grid, to include demand responsive equipment, enhance security and reliability of the energy infrastructure, energy storage research, development, demonstration and deployment, and facilitate recovery from disruptions to the energy supply, and for implementation of programs authorized under title XIII of the Energy Independence and Security Act of 2007 (42
U.S.C. 17381 et seq.): Provided further, That $100,000,000 shall be available for worker training activities: Provided further, That notwithstanding section 3304 of title 5, United States Code, and without regard to the provisions of sections 3309 through 3318
H. R. 1—25
of such title 5, the Secretary of Energy, upon a determination that there is a severe shortage of candidates or a critical hiring need for particular positions, may from within the funds provided, recruit and directly appoint highly qualified individuals into the competitive service: Provided further, That such authority shall not apply to positions in the Excepted Service or the Senior Executive Service: Provided further, That any action authorized herein shall be consistent with the merit principles of section 2301 of such title 5, and the Department shall comply with the public notice requirements of section 3327 of such title 5: Provided further, That for the purpose of facilitating the development of regional transmission plans, the Office of Electricity Delivery and Energy Reliability within the Department of Energy is provided $80,000,000 within the available funds to conduct a resource assessment and an analysis of future demand and transmission requirements after consultation with the Federal Energy Regulatory Commission: Provided further, That the Office of Electricity Delivery and Energy Reliability in coordination with the Federal Energy Regulatory Commission will provide technical assistance to the North American Electric Reliability Corporation, the regional reliability entities, the States, and other transmission owners and operators for the formation of interconnection-based transmission plans for the Eastern and Western Interconnections and ERCOT: Provided further, That such assistance may include modeling, support to regions and States for the development of coordinated State electricity policies, programs, laws, and regulations: Provided further, That $10,000,000 is provided to implement section 1305 of Public Law 110–140: Provided further, That the Secretary of Energy may use or transfer amounts provided under this heading to carry out new authority for transmission improvements, if such authority is enacted in any subsequent Act, consistent with existing fiscal management practices and procedures.
FOSSIL ENERGY RESEARCH AND DEVELOPMENT
For an additional amount for ‘‘Fossil Energy Research and Development’’, $3,400,000,000.
NON-DEFENSE ENVIRONMENTAL CLEANUP
For an additional amount for ‘‘Non-Defense Environmental Cleanup’’, $483,000,000.
URANIUM ENRICHMENT DECONTAMINATION AND DECOMMISSIONING FUND
For an additional amount for ‘‘Uranium Enrichment Decontamination and Decommissioning Fund’’, $390,000,000, of which $70,000,000 shall be available in accordance with title X, subtitle A of the Energy Policy Act of 1992.
SCIENCE
For an additional amount for ‘‘Science’’, $1,600,000,000.
H. R. 1—26
ADVANCED RESEARCH PROJECTS AGENCY—ENERGY
For the Advanced Research Projects Agency—Energy, $400,000,000, as authorized under section 5012 of the America COMPETES Act (42 U.S.C. 16538).
TITLE 17—INNOVATIVE TECHNOLOGY LOAN GUARANTEE PROGRAM
For an additional amount for the cost of guaranteed loans authorized by section 1705 of the Energy Policy Act of 2005, $6,000,000,000, available until expended, to pay the costs of guarantees made under this section: Provided, That of the amount provided for title XVII, $25,000,000 shall be used for administrative expenses in carrying out the guaranteed loan program: Provided further, That of the amounts provided for title XVII, $10,000,000 shall be transferred to and available for administrative expenses for the Advanced Technology Vehicles Manufacturing Loan Program.
OFFICE OF THE INSPECTOR GENERAL
For necessary expenses of the Office of the Inspector General in carrying out the provisions of the Inspector General Act of 1978, as amended, $15,000,000, to remain available until September 30, 2012.
ENVIRONMENTAL AND OTHER DEFENSE ACTIVITIES
DEFENSE ENVIRONMENTAL CLEANUP
For an additional amount for ‘‘Defense Environmental Cleanup,’’ $5,127,000,000.
CONSTRUCTION, REHABILITATION, OPERATION, AND MAINTENANCE, WESTERN AREA POWER ADMINISTRATION
For carrying out the functions authorized by title III, section 302(a)(1)(E) of the Act of August 4, 1977 (42 U.S.C. 7152), and other related activities including conservation and renewable resources programs as authorized, $10,000,000, to remain available until expended: Provided, That the Administrator shall establish such personnel staffing levels as he deems necessary to economically and efficiently complete the activities pursued under the authority granted by section 402 of this Act: Provided further, That this appropriation is non-reimbursable.
GENERAL PROVISIONS—THIS TITLE
SEC. 401. BONNEVILLE POWER ADMINISTRATION BORROWING AUTHORITY. For the purposes of providing funds to assist in financing the construction, acquisition, and replacement of the transmission system of the Bonneville Power Administration and to implement the authority of the Administrator of the Bonneville Power Administration under the Pacific Northwest Electric Power Planning and Conservation Act (16 U.S.C. 839 et seq.), an additional $3,250,000,000 in borrowing authority is made available under the Federal Columbia River Transmission System Act (16 U.S.C. 838 et seq.), to remain outstanding at any time.
H. R. 1—27